Bio-Hydration Research Lab Bio-Hydration Research Lab Bio-Hydration Research Lab Bio-Hydration Research Lab Bio-Hydration Research Lab Bio-Hydration Research Lab

Description

The project consisted of the design and construction of a 17,000 square foot office tenant improvement project and a 171,000 square foot bottling facility. The bottling facility included installation of mechanical, electrical and plumbing systems for a product bottling line, including stainless steel piping, floor trench drains, self-contained bottling room, water storage tanks, DI water system, chillers and electrical connection of bottling line motors and controls. The office portion consisted of the build-out of approximately 17,000 square feet of new office space with a two-story stair and general improvements.

Added Value

Hughes Marino Construction Management (CM) came on board at the request of the client with the project substantially over budget and behind schedule. Hughes Marino CM was able to substantially reduce the budget and got the project back on track and complete within 12 weeks of being hired. Hughes Marino CM also assisted their facilities manager in evaluating their vendor schedules and helped expedite the bottling line assembly and start-up process.

Service Provided

Hughes Marino CM provided project management service from design evaluation and value engineering through permit acquisition and complete project build out.

Project Details

Square Feet - 188,000 SF

Contract Amount - $916,000

General Contractor - BYCOR General Contracting

Architect - Ware and Malcomb

Project Categories

Industry - Biotech

Project Type - Industrial, Tenant Improvement